Greater San Diego Muslim Community Center (“GSDMCC”)

MCC Expansion

Our community is a living testament to unity in faith and dedication to spiritual growth and social welfare. With a substantial increase in attendance and programs, the Muslim Community Center of Greater San Diego has reached a pivotal moment in its history. The expansion of our facilities will serve as a beacon of Islamic learning, worship, and community service.

MCC Architecture Rendering Videos

This project spans a duration of 2 to 4 years, aiming to meet the growing needs of the MCC community. Over the past decade, MCC has experienced substantial growth, making it imperative to enhance capacity for the Masjid and School. As a proactive strategic initiative, this plan anticipates and addresses future growth effectively. Commencing the project at the earliest opportunity ensures better preparation for the projected expansion within the next 2 to 4 years. All funds raised will be diligently managed and accounted for by the Board-approved Treasurer, serving both the Foundation and Operations. Every contribution will directly support the Foundation through a one-time $10,000 membership fee.

 

 

 

A 40% increase in our Al Manar School student population.
Significant growth in our community has led to our existing facilities operating in overcapacity mode 84 days a year. A desire to offer more religious, sports, and youth programs to foster a well-rounded Muslim identity. The need to generate sustainable revenue for long-term financial independence.

Providing a residential space for the dedicated Masjid caretaker.

Construct a new traditional masjid to meet both current and anticipated future needs. Build the Al-Manar School with 12 classrooms and 2 open labs, molding the future of our children with quality education. Restore the existing musallah into a multi-purpose hall, versatile for various community events. Establish facilities to accommodate over 2500 individuals for Eid gatherings. Ensure our caretaker’s well-being with a dedicated residential space, acknowledging their central role in our community.

  • BLDG 1 – Mosque: A mosque with a verandah for reflection and community gathering. Revert existing space to its original purpose as a multipurpose hall. 7510SF (Occupancy – 1090).
  • BLDG 2 – Courtyard: A covered courtyard for year-round activities and events. 4100sf (Occupancy 640).
  • BLDG 3 – School: New Al Manar Weekend School Building. Twelve New Classrooms, Principals, Office, Assistant Principals Office, Break Room, Two large Science Lab, Children Restroom, Kids Playground. Caretaker 2 Bedroom Apartment. (6050SF).
  • BLDG 4 – Ancillary: Includes amenities such as Wudu facilities, a workout area, and a food preparation room alongside a coffee shop for social engagement. (2360SF).
  1. Phase 1: Schematic Design (SD): COMPLETED
    • August 2023: The SD were submitted to the City in August 2023. We are waiting on the comments which we should receive before end of September 2023.
  2. Phase 2: Design Development (DD): 
    • January 2024: The Design Development Phase has started, and various other consultants have been contracted by the Architect. They include civil, structure, landscape, mechanical, plumbing, electrical and IT, Public Address, and Fire Alarm System. We are projecting DD Phase to be completed by end of January 2024.
  3. Phase 3: Construction Document (CD):  
    • Feb 2024 -April 2024: Following completion of DD Phase, the CD Phase will start around beginning of February 2024 and completed by end of April 2024
  4. Phase 4: Building Permit:
    • April 2024 – April 2025: Following complication of CD application for Building Permit will be submitted and we project it will take about a year to get the Building Permit. The project date is end of April 2025.
  5. Phase 5: Bidding:
    •  Once Building Permit is received the project will be Bid to minimum of 3 contractors. The Bids will be received, analyzed and contractor will be interviewed, and final selection made by the GSDMCC Foundation Selection Committee.
  6. Phase 6: Construction:
    • 2nd Half of 2025: It is anticipated that the construction time frame will be about 18 months.

Pay off loan:

  • Accomplished debt-free status, settling a $2.1 million loan burden, Transferred ownership to GSDMCC Foundation, fortifying community autonomy, a turn.

City Approval:

  • Schematic Design drawings were submitted and approved by the City of San Diego Development Services with minor comments.

Townhall Meeting:

  • We have incorporated the request made by the Community into the Final Schematic Design and we have moved into the Design Development Phase of the project.

Support Your Mosque Expansion Plan
With Your Generous Donation